Applies the selected filters and refreshes the display.
Group
Option to group the jobs by one of the following:
Ungroup: No grouping is applied.
Due Date: The date on which production must finish the job.
Req Date: The date by which the customer requires the job.
Customer: Groups jobs by Customer.
Status: Groups jobs based on their statuses.
Rep: Groups jobs by Rep.
Actions
Changes the selected Jobs as follows:
Job Actions
Batch Update: Changes the following fields when Update (button) is clicked and the change is confirmed:
Due Date: Changes the job's Due Date and Time to the ones selected on adjacent calendar and time fields.
Req Date: Changes the job's Required Date and Time to the ones selected on the adjacent calendar and time fields.
Status: Changes the status to the one selected on the dropdown list (Production or Complete).
Set Due Date = Req Date: Sets the Due Dates to match the Required Dates.
Set Start/Finish from Now: Sets the Start Date and Time to now and adjusts the rest of the dates accordingly.
Times are set according to the allocated shifts and amount of time left at the end of the day. If less than 30 minutes, the task is moved to the next day. If more than 30 minutes, the task is split over two or more days.
Set Start/Finish from WO Due Date: Sets the Start Finish times based on the Work Order Due Dates.
Re-create Tasks: Recreates the tasks (e.g. if changes were made that affect the existing tasks).
Update Actions (All Jobs)
Set Start/Finish from Now (Stages): All the tasks are set to now, ordered by Start Date. The Stage is reordered accordingly.
Set Start/Finish by Dependency (Stages): Tasks are moved if the previous task finishes before the next task starts. Cascading tasks, except for Outwork Tasks, are also moved.
Sorting Actions (All Jobs)
Order by Start Date: The Stage is reordered by the Task Start Date.
Order by Status > Start Date: The Stage is reordered by the status and then the Start Date.
Menu
Views: Switches the interface to one of the following views: